The Sterling Shipyard Remediation and Infill Project, located at 2089-2095 Commissioner Street, Vancouver, is a remediation and infilling project on the south shore of Burrard Inlet.
Contact:
604.665.9004
About the project
Subsurface soil in the intertidal area of the project site is contaminated due to historic industrial activity and requires excavation to remediate the site. Once the contaminated soil is removed, the intertidal area will be backfilled with clean engineered fill to create 0.5 hectares of new port industrial land to help continued economic growth amidst an industrial land shortage in the region. The port authority is overseeing this project and, once completed, the new industrial land would be leased to a port tenant or operator.
Hours of work
All general construction and physical activities will take place Monday to Saturday during daytime standard construction hours (7:00 a.m. to 8:00 p.m.) with extended nighttime works permitted for the duration of the construction period.
Additional night or Sunday work will take place on the following dates and times:
Timeline
- Winter 2023 – Project and Environmental Review decision
- Fall 2024 – Construction begins
- Winter 2025 – Project completion
Project work
- Removal of trees and other vegetation on the southern portion of the site
- Installation of erosion and sediment control measures
- Installation of silt curtain around the in-water work area
- Demolition of existing infrastructure
- Installation of temporary shoring around the east and west side of the project area
- Excavation and dredging of approximately 18,000 cubic metres of contaminated substrate from the intertidal and subtidal area of the site, to a maximum depth of 5 metres below grade
- Installation of rock berm revetment approximately 100 metres in length with an elevation of approximately 8 metres
- Placement of approximately 41,000 cubic metres of clean engineered fill in both the intertidal and upland area to elevate the grade to approximately 6 metres
- Grading and compaction of the newly placed engineered fill
- Creation of two subtidal reefs
- Installation of seeded kelp ropes on top of the reefs
- Installation of marine riparian vegetation
- Placement of textured ECOncrete blocks at the foot of the revetment
Habitat offsetting
The project involves the loss of an existing intertidal area. Onsite and offsite habitat will be created to offset effects to fish habitat, in alignment with a Fisheries Act authorization issued by Fisheries and Oceans Canada (DFO).
Two rock reefs will be installed in the subtidal area, lined with seeded kelp ropes. The reefs will provide structural habitat and spaces for fish refuge and spawning, for algae and invertebrates to thrive, and for seaweed/kelp to grow, providing additional habitat for fish, and mobile and encrusting invertebrates.
A marine riparian vegetation zone will also be constructed behind the top edge of the rock berm revetment. The vegetation zone will include numerous species of grasses, sedges, shrubs and trees.
A proposal for the creation of additional offsite habitat has been approved by the port authority, find out more here.
Mitigations
Due to the location of the project site within port lands, construction noise and air quality effects on adjacent communities and businesses would be expected to be limited. Mitigation measures, including an anti-idling policy, a requirement to ensure all equipment is in good working condition, and dust suppression techniques, will be in place for the construction contractor.
Most work is expected to take place during the daytime, though some work is tidal dependent and may need to be done at night.
Construction is expected to begin in August 2024 and is anticipated to take about 10 months. Most works would be done via barge, with the appropriate monitoring plans in place. Deliveries of fill material are anticipated to be done by truck. At this time there are no plans for future development at the site. Any future proposals for development of the site would go through the PER process.
Resources
Technical permit documents
All the technical documents and the Project and Environmental Review permit can be found here.