Vancouver Airport Fuel Facilities Corporation | Vancouver Airport Fuel Delivery Project
Project status
Permit amendment issued
In May 2023, the Vancouver Fraser Port Authority issued amendment PER No. 15-104-02 approving the request to extend the expiry date for the Vancouver Airport Fuel Delivery Project until January 31, 2024. The project consists of the construction of an aviation fuel receiving facility and sections of new transfer and delivery pipelines. The project is located at the end of Williams Road, on Lulu Island in Richmond, British Columbia on federal lands and waters managed by the Vancouver Fraser Port Authority.
Permit Issued
On February 24, 2016, the Vancouver Fraser Port Authority issued a project permit to Vancouver Airport Fuel Facilities Corporation to build elements of their proposed Vancouver Airport Fuel Delivery Project, located at the end of Williams Road, on Lulu Island in Richmond, British Columbia.
Construction of the aviation fuel receiving facility will be conducted in three phases. For more information about proposed construction activities, please visit the Vancouver Airport Fuel Facilities Corporation’s website.
About the project
In February 2011, Vancouver Airport Fuel Facilities Corporation submitted an application for an Environmental Assessment Review for its proposed Vancouver Airport Fuel Delivery Project in Richmond, British Columbia. The Vancouver Fraser Port Authority was the federal lead for the harmonized federal-provincial Environmental Assessment Review led by the British Columbia Environmental Assessment Office.
In December 2013, the port authority concluded its federal environmental assessment review for the Vancouver Airport Fuel Delivery Project and determined that the project is not likely to cause significant adverse environmental effects after the implementation of mitigation measures and environmental conditions. This determination was consistent with the provincial decision rendered on December 12, 2013. For more information, please refer to the harmonized federal-provincial environmental assessment review project page and the British Columbia Environmental Assessment Office website.
In August 2015, Vancouver Airport Fuel Facilities Corporation submitted a project permit application to the port authority to develop an aviation fuel receiving facility and sections of new transfer and delivery pipelines that will be located on federal port land. The proposal also included the construction of an associated office, utilities and landscaping works and the reconfiguration of the downstream range lights, one of which is currently located on the site.
The Vancouver Airport Fuel Facilities Corporation submitted an amendment application to the British Columbia Environmental Assessment Office in April 2016 to address aspects of its proposal that differ from the approved project description attached to the Environmental Assessment Certificate. The British Columbia Environmental Assessment Office approved the amendment application in October 2016. For more information please visit the British Columbia Environmental Assessment Office website.
For additional information on the Vancouver Airport Fuel Delivery Project including details of their construction program, please visit the Vancouver Airport Fuel Facilities Corporation’s website.
Proposed works
Site preparation works
|
Storage tanks
|
Operations facilities
|
Resources
November 2018 – Approved Project Permit Extension (PP15-104): Vancouver Airport Fuel Facilities Corporation Vancouver Airport Fuel Delivery Project [PDF]
February 2016 – Approved Project Permit (PP15-104): Vancouver Airport Fuel Facilities Corporation Vancouver Airport Fuel Delivery Project [PDF]
February 2016 – Approved Drawing Package: Vancouver Airport Fuel Facilities Corporation Vancouver Airport Fuel Delivery Project [PDF]
February 2016 – Project and Environmental Review Report: Vancouver Airport Fuel Facilities Corporation Vancouver Airport Fuel Delivery Project [PDF]
December 2015 – Consideration Memo: Vancouver Airport Fuel Delivery project [PDF]
October 2015 – Engagement Summary Report: Vancouver Airport Fuel Delivery project [PDF]
August 2015 – Section 1: Vancouver Airport Fuel Delivery Project Application Form: Vancouver Airport Fuel Facilities Corporation [PDF]
August 2015 – Sections 2 to 4: Vancouver Airport Fuel Delivery Project Description, Project Design and Study/Report Overview: Vancouver Airport Fuel Facilities Corporation [PDF]
August 2015 – Section 5: Vancouver Airport Fuel Delivery Previous Project Consultation: Vancouver Airport Fuel Facilities Corporation [PDF]
August 2015 – Section 6: Vancouver Airport Fuel Delivery Project Drawings: Vancouver Airport Fuel Facilities Corporation [PDF]
August 2015 – Section 6: Vancouver Airport Fuel Delivery Project Environmental Assessment Decision Statement: Vancouver Airport Fuel Facilities Corporation [PDF]
August 2015 – Section 6: Vancouver Airport Fuel Delivery project Environmental Assessment Conditions: Vancouver Airport Fuel Facilities Corporation [PDF]
August 2015 – Section 6: Vancouver Airport Fuel Delivery project Fire Prevention, Preparedness and Emergency Response: Vancouver Airport Fuel Facilities Corporation [PDF]
August 2015 – Section 6: Vancouver Airport Fuel Delivery project draft Construction Environmental Management Plan: Vancouver Airport Fuel Facilities Corporation [PDF]
August 2015 – Section 6: Vancouver Airport Fuel Delivery project draft Construction Environmental Management Plan Appendices: Vancouver Airport Fuel Facilities Corporation [PDF]
August 2015 – Section 6: Vancouver Airport Fuel Delivery Project Draft Risk and Hazard Analysis for Fuel Receiving Facility Report: Vancouver Airport Fuel Facilities Corporation [PDF]
Contact information
For questions regarding the port authority’ s Project and Environment Review Process, please contact us by email or phone at 604.665.9047. To learn more about the Vancouver Airport Fuel Delivery Project and proposed construction activities, please go to the Vancouver Airport Fuel Facilities Corporation’s website, or contact Mark McCaskill, Senior Project Manager, FSM Management Group Inc. by email or phone 604.271.7113 extension 219.