Upland Owner | New Dock Installation – 1000 Alderside Road

March 10, 2023

Project status
Permit issued

On July 25, 2023, a project permit was issued to the Upland Owner (“the Applicant”) to install a new dock at 1000 Alderside Road, in Port Moody, British Columbia on federal lands and waters managed by the Vancouver Fraser Port Authority.

The project was approved subject to 36 permit conditions the applicant must meet to ensure the project does not result in significant adverse environmental effects. Please see the Impact Assessment Act Registry for the Notice of Intent and Notice of Decision.

About the project

The proposed project includes the following features:  

  • Two aluminum pier sections with punched up porous grated decking, approximately 1.2 metres wide and 17 metres in length, supported by an existing concrete wall and two new precast concrete forms, approximately 760 millimetres in diameter, placed in the intertidal area and filled with concrete  
  • One aluminum access ramp approximately 1.2 metres wide and 15 metres long that would have wheels that would ride in guides placed on the float  
  • A wooden moorage float, approximately 30 square metres, supported in place by concrete mooring blocks and galvanized chain.  

 Contact information
For questions regarding the Project and Environmental Review of the proposed project, or to get in touch with our team, please contact us by email or phone at 604.665.9047.

Please note, when receiving public feedback as part of the PER process, the port authority may collect your personal information, i.e., your name, contact information and personal views and opinions, to inform the PER process for a proposed project. Your personal information may be disclosed to third parties, such as our tenants, in order for them to respond directly to you or help inform our response. You are entitled to submit a complaint to the Privacy Commissioner office here.