Univar | Lynnterm Berth 4 Mooring and Dolphin Upgrades

August 3, 2021

Project status
Permit issued

In September 2021, a project permit was issued to Univar to upgrade existing berthing dolphins at Lynnterm Berth 4, 1545 Bay Street, North Vancouver, on federal waters managed by the Vancouver Fraser Port Authority.

The project was approved subject to 43 permit conditions Univar must meet to ensure the project does not result in significant adverse environmental effects.

Construction is anticipated to take approximately three to four months to complete.

About the project

Univar proposes to upgrade the existing berthing and mooring dolphins to meet current safety code requirements and allow for additional mooring capacity for larger vessels at Lynnterm Berth 4, 1545 Bay Street, North Vancouver. The project includes extending existing fender panels, installing new fender panels, replacing an existing 75 tonne bollard with a 150 tonne rated bollard, installing ten 914 millimeter diameter steel piles, extending concrete pile caps, replacing damaged fender piles, and relocating a gangway, shed and associated equipment.

Contact information

For questions regarding the Project and Environmental Review of the proposed project, or to get in touch with our team, please contact us by email or phone at 604.665.9047.

Please note, when receiving public feedback as part of the PER process, the port authority may collect your personal information, i.e., your name, contact information and personal views and opinions, to inform the PER process for a proposed project. Your personal information may be disclosed to third parties, such as our tenants, in order for them to respond directly to you or help inform our response. You are entitled to submit a complaint to the Privacy Commissioner office here.