Stanley Park Water Supply Tunnel – Chilco Shaft Area

April 15, 2021

Project status

Permit amendment issued

In October 2019, amendment PER No. 19-046-01 was issued to Metro Vancouver . The amendment approved to amend the scope, revise condition No. 21, and extend the expiry date of Project Permit PER No.19-046. The project is located Stanley Park Water Supply tunnel, from the south side to the east side of Lost Lagoon, British Columbia on federal lands and waters managed by the Vancouver Fraser Port Authority.

About the amendment:  the Greater Vancouver Water District (GVWD, the Permit Holder) is planning to construct a new water main below the surface of Lost Lagoon at Stanley Park. This Project was captured under PER No. 19-046 – Stanley Park Water Supply Tunnel Chilco Shaft Area, however the Permit Holder has requested to amend the Project Permit to add additional scope components, amend condition #21 of the Project Permit to allow flexibility on the retention of existing utilities and extend the proposed completion date of the Project.

Permit issued

In September 2021, a project permit was issued to the Greater Vancouver Water District to construct a major water infrastructure project, referred to as the Stanley Park Water Supply Tunnel. The work will replace a section of existing water supply infrastructure. When complete, the new tunnel will meet current seismic standards, help ensure the continued reliable delivery of clean, safe drinking water to the region, and increase the capacity of the existing system to support the region’s growing population. The project is located south of Lost Lagoon (Stanley Park) and adjacent to Chilco Street, Vancouver, BC, on federal lands managed by the Vancouver Fraser Port Authority.

The project was approved subject to 36 permit conditions that the Greater Vancouver Water District must meet to ensure the project does not result in significant adverse environmental effects. Please see the Impact Assessment Act Registry for the Notice of Intent and Notice of Decision.

About the project

The Greater Vancouver Water District is planning to construct a major water infrastructure project, referred to as the Stanley Park Water Supply Tunnel, to replace a section of existing water supply infrastructure. The Project involves the excavation of a 1,400 metre long, 4.2 metre diameter, water supply tunnel that will range between 45 to 50 metres below the ground surface of Stanley Park, connected to three access shaft areas. The Chilco Shaft Area is located within the port authority’s jurisdiction.

Works include:

While the majority of the Project works are outside Port Authority jurisdiction, the Project works located within Port Authority jurisdiction include:

  • Tunneling approximately 390 m under Lost Lagoon;
  • Construction laydown area, which will include:
    • installation of construction fencing,
    • vegetation removal,
    • tree clearing and
    • temporary site grading.
  • Movement of construction vehicles;
  • Construction of temporary pedestrian and cyclist pathways, each approximately 150 m long (new permanent pathways will be reinstated to existing configuration once construction work has completed);
  • Replacement of approximately 75 m of the existing West End Interceptor No. 1 (1,067 mm dia combined storm / sanitary pipe) in the construction laydown area;
  • Potential protection / replacement of approximately 75 m of the existing West End Interceptor No. 2 (610 mm dia);
  • Installation of temporary instrumentation to support the excavation works;
  • Identification of utilities (potholing, hydrovac etc.) and protection / relocation / replacement;
  • Discharge of construction water, and potentially water main disinfection, into Lost Lagoon / Burrard Inlet through West End Interceptor No. 1, or through a temporary line, if sanitary discharge is not possible via sanitary main – West End Interceptor No. 2 (the disinfection procedure has yet to be determined); and
  • Final regrading and landscaping, including the installation of minor hardscape elements (i.e. benches, retaining walls, etc.).

The expected footprint of the Chilco Shaft Area is 2,900 square metres and the length of the supply tunnel portion located within Port Authority managed land is approximately 390 m.

Contact information

For questions regarding the Project and Environmental Review of the proposed project, please contact PER by email or phone at 604.665.9047.