June 3, 2020

Permit issued

In July 2020, a project permit was issued to Beedie Development in care of Fraser Mills Properties Ltd., to remove approximately 300 creosote treated timber piles from the Fraser River fronting River Front Park in Coquitlam, British Columbia on federal lands and waters managed by the Vancouver Fraser Port Authority.

The project was approved subject to 40 permit conditions that Beedie Development must meet to ensure the project does not result in significant adverse environmental effects.

About the project

Beedie Development in care of Fraser Mills Properties Ltd. proposes to remove approximately 300 creosote treated timber piles from the Fraser River fronting River Front Park in Coquitlam.

The piles will be removed from a previous log storage area to make-way for shoreline improvements associated with an upland development. The works are proposed to be conducted by barge with vibratory and cable extraction. Deteriorated piles, that cannot be removed by extraction, are proposed to be cut at the mudline by pile snipper and capped with clean sand to a minimum depth of 30 centimeters. Extracted piles will be disposed of at an appropriate facility.

For questions regarding the Project and Environmental Review of the proposed project, please contact Lisa McCuaig, Environmental Specialist, by email or phone at 604.353.8958.