The Vancouver Fraser Port Authority is delivering the Holdom Overpass Project in partnership with the City of Burnaby, CN, and the Government of Canada. This new four-lane overpass will improve traffic flow and safety for the Burnaby community, and increase trade capacity and efficiency. 

Construction on the project began in December 2024. Based on the feedback received during public engagement, we will continue to provide information on upcoming construction activities and traffic impacts on this webpage to make sure the community is kept up to date. Please note that the activities and schedule are subject to change. To receive these updates via email, sign up for our monthly newsletter. 

Please travel slowly through the area, use caution, and obey signage and traffic personnel. Users of the Central Valley Greenway are asked to reduce speed and watch for changes along the pathway, such as new signage, traffic calming infrastructure, and ground conditions. We thank you in advance for your cooperation and understanding.

Multiple locations

Site prep 
Image
Ground improvements map
  • Where: Along Central Valley Greenway, and near Douglas Rd. and Norland Ave.
  • When: January 8 to mid-April, 7 a.m. to 5 p.m.
  • What’s happening: Ground improvements
  • What to expect:
    • Expect increased noise (consistent with typical construction activities) and increased traffic volumes as construction equipment mobilizes to site
    • Local access to driveways will be maintained
    • Traffic control personnel will maintain all crosswalks, coordinate access for emergency vehicles, and direct the movement of equipment and workers as required
    • These construction activities will not impact cycling or pedestrian access to the Central Valley Greenway, including the portion of the path between Douglas and Kensington
    • Northbound bus stop on Douglas Rd. has been temporarily relocated approximately 100m north (south of Still Creek Ave.). Bus operations for the #133 route will not be impacted in the area.

 

Pile driving
  • Where/when:
    • Along Central Valley Greenway (see map 2), beginning early April
    • East side of Holdom Ave. (north of Kingsland Dr.; see map 3), beginning week of March 17 to mid-April
  • Timing: Ongoing intermittently (Monday to Friday from 7 a.m. to 8 p.m., and Saturday from 9 a.m. and 8 p.m.)
  • What’s happening: Pile driving activities are required to build the overpass structure foundation and the new Goring Pump Station foundation
  • What to expect:
    • Expect increased noise (consistent with typical construction activities). Most pile driving will be carried out with equipment that results in moderate noise levels, with louder equipment only used when necessary. Noise levels will be monitored and evaluated to ensure equipment operates within noise variance limits.
    • Expect low-level vibration in the immediate vicinity of pile driving activity
    • Traffic control personnel will direct the movement of equipment and workers, and coordinate access for emergency vehicles as needed
Image
Location of piling for Holdom Overpass Project

Map 2: Areas where pile driving activity will occur near the Central Valley Greenway

Image
3 - Holdom north

Map 3: Areas where pile driving activity will occur near Holdom Ave. 

Kingsland Drive

Lane shift
Image
Aerial of Holdom traffic construction zone
  • Where: On Kingsland Dr., east of Holdom Ave.
  • When: Beginning on March 12, ongoing on a 24-hour basis until fall 2025
  • What’s happening: Existing roadway will be shifted south. Two-way traffic will be maintained. Safety barriers will be installed on the north side of Kingsland Dr. Construction activities will begin in the area, e.g., relocating utilities.
  • What to expect
    • Expect increased noise (consistent with typical construction activities) and increased traffic volumes as construction equipment mobilizes to site 
    • Local access to driveways will be maintained 
    • Traffic control personnel will maintain all crosswalks, coordinate access for emergency vehicles, and direct the movement of equipment and workers as required
    • Signage will be in place prior to the closure to inform drivers of any traffic pattern changes

Central Valley Greenway

Temporary detour
Image
4 - CVG cycling French
  • Where: East of Douglas Rd.
  • When: Beginning March 26, ongoing on a 24-hour basis
  • What’s happening: Temporary detour to provide continuous access for Central Valley Greenway users. Existing path will be extended through an adjacent property, connecting to Douglas Rd. and Still Creek Ave. intersection.
  • What to expect:
    • Portions of the existing pathway will be temporarily closed while the detour is in effect
    • Stage 1 detour (blue route on map) will be used initially, beginning on March 26 for approximately two weeks. Central Valley Greenway users will follow a follow a temporary extension of the path through areas where project clearing activities have already taken place.
    • Stage 2 detour (green route on map) is expected to begin on April 11. Involves a temporary extension of the existing pathway through the adjacent property at 2636 Douglas Rd.
    • For the safety of Central Valley Greenway users, detours will be fenced and traffic control personnel will direct the movement of equipment and workers, as required, while activities are taking place
    • Signage will be in place prior to the closure to inform Central Valley Greenway users of the temporary detour

Douglas Road and Norland Avenue

Image
5 - Holdom south
Lane shifts 
  • Where: Douglas Rd. (between Still Creek and Regent St.) and Norland Ave. (east of Douglas Rd.)
  • When: Beginning in mid-May, ongoing on a 24-hour basis
  • What’s happening: Lane shifts and reconfiguration of Douglas Rd. at Norland Ave. intersection to allow for construction activity at the locations shown on the map. All traffic movements will be maintained in all directions throughout the area.
  • What to expect:
    • Prior to this traffic pattern change, intermittent lane shifts and/or lane closures will be required on Douglas and Norland for several days in May
    • Pedestrian access will be maintained via the crosswalks on the south and east sides of the Douglas and Norland intersection. The crosswalk and traffic island on the north side of the intersection will be removed.
    • Expect increased noise (consistent with typical construction activities) and increased traffic volumes as construction equipment mobilizes to site
    • Local access to driveways will be maintained
    • Traffic control personnel will direct the movement of equipment and workers, and coordinate access for emergency vehicles as needed

 

About the Holdom Overpass Project

The Vancouver Fraser Port Authority is delivering the Holdom Overpass Project in partnership with the City of Burnaby, CN, and the Government of Canada, as part of the Burnaby Rail Corridor Improvements Project. Once complete, the new four-lane overpass will improve traffic flow and safety for the Burnaby community, and increase trade capacity and efficiency. Aecon-Gateway Infrastructure Group Partnership is the design-build contractor.

Contact

phone 604.665.9004
email [email protected]
computer portvancouver.com/holdomoverpass

If you know someone who would like to receive these project updates, please invite them to subscribe to the newsletter.